Project Recovery
Health check, root causes and a recovery plan for delayed projects.
AI Recovery Diagnosis
Recovery is realistic if interim specialists start by 30 November. Schedule performance is expected to return to 0.95 by February 2027.
6-Dimension Project Health Check
Needs recovery
Overall: 2.7 / 5
Scope
4
Schedule
2
Cost
2
Quality
3
Risks
2
Stakeholders
3
Schedule Performance Forecast through Feb 2027
Target: 0.95Jun0.96
Jul0.93
Aug0.9
Sep0.86
Oct0.82
Nov0.78
Dec0.84
Jan0.9
Feb0.95
Root Causes of Delay
- 1Shortage of certified cybersecurity specialists (linked to R01).
- 2Vendor onboarding took 5 weeks longer than planned.
- 3The security assessment scope grew after internal audit findings.
Recovery Action Plan
| # | Step | Owner | Due | Status |
|---|---|---|---|---|
| 1 | Engage interim specialists through the approved vendor | Maryam Al Shamsi | 2026-11-30 | In progress |
| 2 | Re-baseline the schedule with the 6-week extension (CR-02) | Layla Al Hosani | 2026-11-25 | Awaiting approval |
| 3 | Weekly recovery check-in with the sponsor | Omar Al Ketbi | 2026-11-24 | Not started |
| 4 | Split the assessment into two phases | Maryam Al Shamsi | 2026-12-05 | Not started |
Recovery Plan Sign-Off
Recovery planREC-P04P04
Your turn1 day
Recovery plan: Cybersecurity Readiness Program
Engage interim specialists, re-baseline schedule with 6-week extension (CR-02), and split assessment into 2 phases.