Project Recovery

Health check, root causes and a recovery plan for delayed projects.

AI Recovery Diagnosis

Recovery is realistic if interim specialists start by 30 November. Schedule performance is expected to return to 0.95 by February 2027.

6-Dimension Project Health Check

Needs recovery
Overall: 2.7 / 5
Scope
4
Schedule
2
Cost
2
Quality
3
Risks
2
Stakeholders
3

Schedule Performance Forecast through Feb 2027

Target: 0.95
Jun0.96
Jul0.93
Aug0.9
Sep0.86
Oct0.82
Nov0.78
Dec0.84
Jan0.9
Feb0.95

Root Causes of Delay

  1. 1Shortage of certified cybersecurity specialists (linked to R01).
  2. 2Vendor onboarding took 5 weeks longer than planned.
  3. 3The security assessment scope grew after internal audit findings.

Recovery Action Plan

#StepOwnerDueStatus
1Engage interim specialists through the approved vendorMaryam Al Shamsi2026-11-30In progress
2Re-baseline the schedule with the 6-week extension (CR-02)Layla Al Hosani2026-11-25Awaiting approval
3Weekly recovery check-in with the sponsorOmar Al Ketbi2026-11-24Not started
4Split the assessment into two phasesMaryam Al Shamsi2026-12-05Not started

Recovery Plan Sign-Off

Recovery planREC-P04P04
Your turn1 day

Recovery plan: Cybersecurity Readiness Program

Engage interim specialists, re-baseline schedule with 6-week extension (CR-02), and split assessment into 2 phases.